New Facility Information

RFIS is currently working o­n the construction of a new facility. Located approximately 8 kilometers from our current location, the new campus will accommodate approximately 150 students and is 6 ½ hectares (about 16 acres) in size. When completed the school will have ten regular classrooms, two science labs, an art room, a living skills classroom, a computer lab, a library-media center, an administration building, a large auditorium and music building, a full-size soccer field, a physical education practice field, a covered gym, field house (student gym lockers and showers), complete wood and industrial arts facilities, a student center, an aquatics center, and 4 tennis courts. Total cost to build the entire new facility is estimated to be $2,338,000.00 US dollars.

We have completed Phase 1 (the purchase of the land), and Phase 2 (building the necessary infrastructure). We are beginning on Phase 3 (construction of essential buildings) which will allow us to actually move to the new facility. We would like to make the move in June-July of 2009. Phase 4 (completion of the campus) will be pursued as money becomes available.

Some buildings, like the high school classroom block and auditorium, will not be built until after we move to the site and funds become available. We will be assigning some spaces for an initial use to make the move, and then ‘reallocating’ space as we grow, building what we need. So the upstairs of the library will start out as the auditorium, and when the auditorium is built, this space will be used for additional library shelves or classrooms.

The school currently has enough funds to complete most of Phase 3. If you would like to participate in providing funds for the new facility please contact the Development Officer, Mr. Vince Griffis at: This e-mail address is being protected from spambots. You need JavaScript enabled to view it

Construction will be supervised by Paul Dubois with Wycliffe Associates. Wycliffe Associates is a support organization for Wycliffe Bible Translators.

For individuals who would like to come help build the new facilities or you want more information write to This e-mail address is being protected from spambots. You need JavaScript enabled to view it and address it to Jim Hubbard. If you want more information o­n an established team that is already coming or you want to bring a team (from a church, etc, or anything else relating to project teams write to the Africa Area team coordinator: This e-mail address is being protected from spambots. You need JavaScript enabled to view it .

More questions? Ask! The WA website is at: wycliffeassociates.org. You can also find individual and team opportunities under Service Opportunities o­n the WA web site.

We are looking to God’s people to provide the funding for the new RFIS facilities as we continue “Serving Those Who Serve” the people of Central Africa.


      Prayer Items


  • Pray for the binding of spiritual powers tied to the property, and for our equipment to not have any delays, breakdowns, or ailments of any kind.
  • Pray for our workers--for peace, safety, dedication to the work, concientiousness in work, and their relationships with God. Also, for peace at the gate as many people will be coming to ask for work.
  • Pray for our material deliveries and availabilities, US purchases to ship and arrive in timely manners, and money for the project to finish.
  • Pray for qualified volunteers to come and serve in many ways, and for skilled workers to be able to increase their skills.
  • Pray for the managers of the project: that their requirements would be clear, communicable, and sensitive to appropriate local concerns.
  • Supervisor Paul Dubois, as he assumes extra responsibilities for WA for the next few months (volunteer coordinator is o­n furlough in the US)
Last Updated 17 March 2008
 


 

 


 

  • Phase 1
    • Land Purchase
    • Total cost of land: $335,000.00 The school has a remaining debt of $24,000.00
  • Phase 2
    • Earthwork for football pitch and practice field. - Plant grass in football pitch and practice field - Earthwork for internal road - Security walls - Install electrical service – Guardhouses and entry gates - Water system – Start industrial arts area (this will be used to build the facility)
    • $275,000.00
  • Phase 3
    • Library - Middle school block – Science - Admin building - Uncovered gym - Employee building - Field house (student gym lockers and showers) - Storage yard – Teachers’ area – Walkways – Parking areas – Additional slab and buildings for industrial arts area.
    • $898,000.00
  • Phase 4
    • Cover gym – Auditorium – High school block – Finish industrial arts area – 4 tennis courts – larger water storage tank – aquatics center – outdoor basketball courts– sand volleyball court – Additional landscaping.
    • $830,000.00

 Click here to see photos of the new site